When a deck in Christchurch needs a building consent, when it needs a balustrade, and when the district plan applies. The 1.5 metre rule explained.

In short

  • No building consent if a fall of more than 1.5 m is not possible.
  • A balustrade is required where a fall of 1 m or more is possible.
  • Every deck must still meet the Building Code.

Most decks in Christchurch do not need a building consent. The test is height, and it is the same across New Zealand.

The 1.5 metre rule

Schedule 1 of the Building Act exempts a deck from building consent when it is not possible to fall more than 1.5 metres from it, even if it collapses. Christchurch City Council applies the same test. It is measured from the deck surface to the ground at the lowest point beside it, so on a sloping section the downhill edge is the one that counts.

Possible fall from the deckBuilding consentBalustrade
Under 1 mNot requiredNot required
1 m to 1.5 mNot requiredRequired
More than 1.5 mRequiredRequired

Exempt does not mean unregulated

A deck built without a consent still has to comply with the Building Code. That covers structure, durability and safety from falling. If it is built badly, the council can require it to be fixed, and it can come up when you sell.

Balustrades

Where someone could fall a metre or more, the Building Code requires a barrier. On a deck attached to a house it must be at least 1 metre high, with gaps small enough that a 100 mm ball cannot pass through and nothing a small child could climb.

When you do need a consent

You apply to the council with drawings that show the structure, the fixings and the balustrade. Engineering may be required for tall or unusual decks. The council has 20 working days to process an application once it has everything it needs, and it inspects the work during the build. A Code Compliance Certificate is issued at the end.

The district plan is separate

A building consent deals with how a deck is built. The district plan deals with where it can go. A raised deck or a roofed pergola can be subject to rules on boundary setbacks, height and site coverage, and may need a resource consent even when no building consent is required. See how close to the boundary you can build.

Other things to check

  • Pools. A deck that forms part of a pool barrier must meet the pool fencing rules, and pool barriers need a consent.
  • Roofs. A roof over a deck has its own exemption limits. See pergolas.
  • Pipes and drains. Do not build over council drains or manholes without checking. Your property file shows where they run.
  • Covenants and cross-leases. Subdivision covenants and cross-lease titles can restrict what you build.
  • Outside the city. Rolleston and Lincoln come under Selwyn District Council; Rangiora and Kaiapoi under Waimakariri District Council. The 1.5 metre rule is the same; planning rules differ.

This is general information. Rules change, so confirm with the council or your builder before you start.

Common questions

How high can a deck be without a consent in NZ?

There is no fixed deck height. The test is whether a person could fall more than 1.5 metres from it. If not, no building consent is needed.

Do I need a consent to replace an existing deck?

Replacing a deck with a comparable one in the same place is generally exempt. If the old deck needed a consent because of its height, check with the council first.

Does a low deck need to meet the Building Code?

Yes. All building work must comply with the Building Code whether or not it needs a consent.

Who checks an exempt deck?

Nobody inspects it, which is why the builder you choose matters. Keep photos of the piles and frame before the boards go on.

Want a firm price for your deck?

Send the form and we will arrange a free site visit and a written, itemised quote. Or ring and talk it through.

Call 03 660 1238

Request a free quote

Tell us about the job. We reply within one working day.

Free site visit and written quote · No obligation

Call nowFree quote